This month, we are continuing work on the restoration of the mosaic tile and installing new black granite on the northwest corner of the Saban Building.

Installation of interior framing and fireproofing continues to progress throughout the building, as well as construction, wall buildout, and acoustic spray of restrooms and administrative offices. Building of guardrails on the spine of the Saban Building and scaffolding on the north façade for upcoming plaster work will continue through May.

On our Sphere Building, work on the garter dome embeds is ongoing and our third concrete pour will occur this week with a subsequent pour happening in the coming weeks.

Simultaneous to the Academy Museum’s construction, Metro continues work on the forthcoming Purple Line Extension. Visit https://www.metro.net/purple for more information about Purple Line Extension construction. Thank you for your continued support as we build the Academy Museum of Motion Pictures.

Comments are closed.