Academy Museum Update

November 9, 2017 by  
Filed under Miscellaneous

This month, caulking of the precast panel joints on the west side of the spherical building will be completed. Concrete for the building’s projection box and screen box slabs has been poured, and embeds for an antenna mast will be installed in the projection box walls.

Installation of the Saban Building’s escalator system is now complete. Structural steel for the air handler and cooling tower is being erected on the building’s roof, and installation of the limestone anchors of the south façade is being completed.

Simultaneous to the Academy Museum’s construction, Metro continues work on the forthcoming Purple Line Extension. Visit https://www.metro.net/projects/westside/field-work/ for more information about Purple Line Extension construction. Thank you for your continued support as we build the Academy Museum of Motion Pictures.